The Santa Clara Valley Water District, known as Valley Water, has awarded a $1.9 billion contract for the Anderson Dam Seismic Retrofit. A joint venture between FlatironDragados and Sukut Construction will deliver the project in Morgan Hill, California.
Valley Water selected the joint venture through a best-value procurement process and issued a notice to proceed. The contractors will rebuild major portions of the dam to meet current seismic safety standards. Work will include reconstructing the embankment and spillway and installing new outlet infrastructure. The team will also complete roadway, utility, and environmental improvements.
The wider Anderson Dam project carries an estimated cost of $2.8 billion. This total includes associated work such as the Anderson Dam Tunnel, which falls outside the $1.9 billion retrofit contract.
FlatironDragados began building the 1,700-foot-long, 24-foot-diameter tunnel in 2021. The company expects to complete the tunnel before major retrofit construction begins. The permanent low-level outlet will help Valley Water manage reservoir levels during and after the dam work. Valley Water expects retrofit construction to begin in early 2027.
Anderson Reservoir provides water supply, groundwater recharge, and incidental flood protection for nearly two million residents. Valley Water reduced the reservoir to 3% of capacity in 2020 because of seismic safety concerns.