The San Francisco Public Utilities Commission (SFPUC) selected a joint venture of Jacobs and PCL Construction to design and build upgrades at the Southeast Treatment Plant. The commission estimates the progressive design-build project will cost $1 billion.
The joint venture will add a treatment process to reduce the amount of inorganic nitrogen the plant discharges into San Francisco Bay. SFPUC says the process will meet updated state and federal environmental requirements. The commission’s new treatment plant on Treasure Island also removes nutrients from wastewater.
The Southeast Treatment Plant handles nearly 80% of San Francisco’s wastewater and will continue operating during construction. Both contractors have previously worked with SFPUC on wastewater projects, and Jacobs has carried out earlier upgrades at the Southeast plant.
Jacobs will also fund local health, education, and workforce training initiatives through SFPUC’s Social Impact Partnership.